Infrastructure, And Water Supply, Treatment, And Distribution Projects

  • Industrial and Medical Wastewater Treatment Plants

    The project for constructing industrial and medical wastewater treatment plants have been designed and funded based on the state of the art technology in line with the goals of the company for protecting the environment. The total area of this project is 2,500 square meters, and it is in final stages of implementation.

  • Intake Pumps (Pumps for collecting water from the sea)

    This project includes two pumps, each with a capacity of 6,600 cubic meters per hour, for collecting water from the see and transferring the water from the pumps to the coastal line with a length of 1.5 km. One of the pumps is currently active, while the second one is being installed.

  • RO2 Desalination System with a capacity of 34,000 cubic water of Demin water each day

    ultimately provide 34,000 cubic meters of Demin water a day, and it includes two phases, each with a capacity of producing 17,000 cubic meters of water. The first phase of this project was completed in 2015 with the goal of supplying the water required for the first phase of the steelmaking plant, and it has been active ever since. The second phase will be completed in March, 2021.

  • RO1 Desalination System with a capacity of 30,000 cubic meters of industrial water a day

    The construction of this project with a production capacity of 30,000 cubic meters of water a day started in 2015, and it is predicted that it will be completed in March, 2021.